Bathroom Retreat

Build a spa-worthy experience

Coordinate tile, plumbing fixtures, waterproofing, and ventilation for a bathroom that feels like a retreat.

Moisture-smart design with luxurious finishes.

Waterproofing

Specify shower systems and membranes early so tile installers have everything on hand day one.

Fixture compatibility

Match valves, trims, and drain kits across brands to avoid last-minute trips to the supply house.

Ventilation

Size exhaust fans correctly and plan ducting to keep humidity under control.

Avg. budget

$28k+5% YoY

Primary bath with tiled shower

Timeline

6-8 weeks

Tile-heavy projects push longer

Common risk

Lead-time fixtures

Order valves alongside trims

Budget guardrails

Efficient refresh

$12k - $18k

New vanity, plumbing trim, lighting, paint, and minimal tile work.

Primary suite

$24k - $38k

Custom tile shower, freestanding tub, double vanity, and radiant floor heat.

Luxury spa

$40k - $65k

Steam shower, smart controls, custom cabinetry, and stone slab details.

Recommended timeline

Planning

2 weeks

Measure existing bath, select fixtures, and confirm plumbing configuration.

Rough-in

2 weeks

Demo, framing, plumbing, electrical, and radiant install before inspections.

Tile & finishes

2-3 weeks

Waterproofing, tile setting, trim, glass, and millwork.

Closeout

1 week

Final plumbing trim, punchlist, glass install, and clean.

What success looks like

Moisture management

Pair waterproofing systems with appropriate thinset, grout, and sealers for longevity.

Comfort features

Heated floors, towel warmers, and layered lighting elevate everyday rituals.

Storage planning

Use recessed niches, vanity towers, and medicine cabinets to keep surfaces clutter-free.

Pre-build checklist

Confirm drain locations before concrete work

Order custom glass once tile dimensions are confirmed

Schedule waterproofing inspection pre-tile

Protect finished tile during trim installs